Point Cook
ADDRESS
Point Cook Telstra Store
DATE COMPLETED
June 2020
BUILDER
Q1 Built
BUILD COST
500,000
BUILD COST
Retail refurbishment
DESCRIPTION
Working with the builder prior to the project’s commencement was important, so we are able to order in all of the items that were required for the project before commencement. We had to pre order everything as the timeframe was only two weeks for handover. We also had to create some contingency plans if something
was to go wrong- this ensured the whole project kept moving without delay.